- Installation of two hot taps (10″ on 10″ and 10″ on 16″)
- Risers and above ground piping/valves
- Pre-fabricated flow control skid
- Pre-fabricated EGM/Gas Chromotograph Building
- Associated Electrical/Civil work
With 4,858 total manhours, the project was completed incident-free without environmental impact.